DePuy Johnson & Johnson

DePuy Johnson & Johnson Biomass Boiler

Loughbeg, Ringaskiddy, Co. Cork

 

In late 2009 DePuy Ireland, a Johnson & Johnson company contracted John Sisk & Son to erect a biomass energy centre to replace the aging gas fired boilers. This new energy centre is designed provide the manufacturing plant with the required process heat.

The Sisk procurement process resulted in the appointment of Filtrex as boiler supplier and M&E contractor for the project and a key member of the design team.

Filtrex were able to meet and exceed the design requirements by using a 2 x Herz Biomatic 500kW woodchip boilers in conjunction with a 7500l fully insulated hot water buffer tank.

During the detailed design process it became clear that traditional delivery methods for woodchip would not be possible on this site and Filtrex were given the task of engineering a solution that would meet the clients “Zero Access” policy and unload a 20 tonne 100m³ trailer in less than one hour.

Filtrex designed an unloading station using Vecoplan equipment including conveyor metering, chain conveyors and a control station that allows the driver to optimise the offloading. Interlocking panels conceal all moving parts that comply with the clients Health & Safety policy allow the driver to perform the unloading unattended.

 

Project Specifics:

Design, installation and commissioning of biomass heating plant capable of generating 850kW of thermal energy fuelled by woodchip

The final installation consisted of:

  • 2 no. 500kW Herz Biomatic woodchip biomass boilers
  • 1 no. 7500l hot water buffer
  • Woodchip fuel storage bunker fit-out
  • Vecoplan woodchip reception system offloading 10t/hr
  • Full M&E installation for boilerhouse and storage bunker
  • Twin Wall Stainless Steel Flue

Commissioned : October 2010

 

“After meeting and spending time with the Filtrex design team we were confident that the installation of the boilers and the tie-in with the manufacturing plant would run smoothly…it was a bonus to have a company on the design team that were experienced in handling large bulk volumes of woodchip ”

Eamon Power, Senior M&E Engineer at John Sisk & Son

 

Filtrex Twitter Feed